Most inquiries are responded to within two business days. However, some questions require further investigation or clarification.
Chongqing Electric needed extra capacity to meet anticipated heavy power demand for the summer Olympics in Beijing and did not have time to construct new towers. This installation serves more than a half million residents within two districts in Chongqing City, an ancient city with a population of approximately four million located on the Yangtze River in southwest China, within Sichuan Province. Chongqing is in a subtropical region with high humidity and frequently extreme summer heat, and 3M ACCR was chosen in part because of its proven reliability in difficult climates.
Our dedicated technical team is here to help you approach your next project with confidence. Get in-depth product information, valuable application guidance, training options and more.